Beginning Monday, June 25 thru Friday, June 29 the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Excavation and Utility Work
  • Wilshire Blvd./La Brea Ave. – Concrete Work, Rebar Steel Deliveries and Underground Support at Wilshire Blvd./Sycamore Ave.
  • Wilshire Blvd./Fairfax Ave. – Excavation and Hauling
  • Wilshire Blvd./La Jolla Ave. – Jet Grouting

Wilshire Blvd./La Cienega Blvd. and Wilshire Blvd./Stanley Dr. – Excavation, Hauling, Dewatering Well Maintenance and Jet Grouting Preparation