Purple Line Construction Week Look-Ahead 6/4 – 6/8

Beginning Monday, June 4 through Friday, June 8 the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Excavation, Instrumentation Work and Utility Work
  • Wilshire Blvd./La Brea Ave. – Concrete Work, Rebar Steel Deliveries and Underground Support at Wilshire Blvd./Sycamore Ave.
  • Wilshire Blvd./Fairfax Ave. – Excavation and Hauling
  • Wilshire Blvd./La Jolla Ave. – Jet Grouting

Wilshire Blvd./La Cienega Blvd. – Excavation, Hauling and Utility Work


For more information click here