Beginning Monday, March 19 thru Friday, March 23 the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Excavation, Instrumentation and Utility Work
  • Wilshire Blvd./Norton Ave. – Work Zone Removal
  • Wilshire Blvd./Rimpau Ave. –  Instrumentation Work
  • Wilshire Blvd./La Brea Ave. – Concrete Work, Rebar Steel Deliveries and Underground Support at Wilshire Blvd./Sycamore Ave.
  • Wilshire Blvd./Fairfax Ave. – Excavation and Hauling
  • Wilshire Blvd./La Jolla Ave. – Jet Grouting Preparation

Wilshire Blvd./La Cienega Blvd. – Excavation, Instrumentation, Hauling, Utility Hanging and Street Restriping