Metro Purple Line Update 9/18 – 9/22

Construction Week Look-Ahead 9/18 – 9/22

Summary

Beginning Monday, September 18th thru Friday, September 22nd the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Instrumentation Work
  • Wilshire Blvd./Highland Ave. – Instrumentation Work
  • Wilshire Blvd./La Brea Ave. – Excavation and Hauling
  • Wilshire Blvd./Cloverdale Ave. – Potholing and Jet Grouting Preparation
  • Wilshire Blvd./Fairfax Ave. –  Excavation, Hauling and Wilshire Blvd. Deck Opening
  • Wilshire Blvd./La Cienega Blvd. – Potholing, Piling, Instrumentation and Steel Deliveries