Fairfax Decking is Complete!

Fairfax Decking has been completed five weekends earlier than originally scheduled. This wouldn’t have happened without collaboration amongst the numerous LA City Departments and elected officials staff from CD4 and CD5 who work so closely with this project!

This success is also due to excellent planning by the design-build contractor STS and a solid working relationship and patience of community/stakeholders. The decking operation included excavating a portion of the roadway and replacing it with concrete deck panels that will act as a temporary street surface while underground station excavation continues below.

To find out exactly how many deck panels were used to cover Wilshire/Fairfax, check out the full coverage and pictures from Metro’s The Source