Beginning Monday, December 18th thru Friday, December 22nd the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Preparation for Pile Installation
  • Wilshire Blvd./Norton Ave. – Jet Grouting
  • Instrumentation work at Wilshire Blvd./Tremaine Ave.
  • Wilshire Blvd./Fairfax Ave. –  Excavation, Hauling, Instrumentation Work and Deck Maintenance
  • Wilshire Blvd./La Brea Ave. – Concrete Work and Dewatering Well Maintenance at Wilshire Blvd./Sycamore Ave.

Wilshire Blvd./La Cienega Blvd. – Decking Preparation, Utility Work, Hauling and Dewatering Well Installation