Purple Line Construction Weekly Updates for 11/6-11/10

Beginning Monday, November 6th thru Friday, November 10th the design-builder will be conducting:

  • Wilshire Blvd./Western Ave. – Utility (Sewer) Relocation and Preparation for Pile Installation
  • Wilshire Blvd./Rossmore Blvd. – Instrumentation Work
  • Wilshire Blvd./Orange St. – Repair of Storm Drain Under Wilshire Blvd.
  • Wilshire Blvd./La Brea Ave. – Excavation and Concrete Work from the Center Opening
  • Wilshire Blvd./Cloverdale Ave. – Median Landscaping
  • Wilshire Blvd./Fairfax Ave. –  Excavation and Hauling

Wilshire Blvd./La Cienega Blvd. – Decking Preparation, Utility Work and Hauling

 